Project dependency

A project dependency describes how a task or decision is tied to other results, dates or resources.

IT Consulting & Strategy

Make prerequisites and bottlenecks visible

A project dependency connects work, decisions or required resources. In a fictional example, the team can only make its final assessment of an interface test once the business field definition is approved. The test therefore has a content-related prerequisite.

A shared staffing bottleneck is a different type of constraint: independent tasks still cannot be performed simultaneously by the same fully occupied person. Both can affect planning. Record the required result or resource, responsible role, expected timing and consequence of delay. An arrow in a plan does not establish that the prerequisite has actually been met. Check its status before the dependent step.